/Calculateur de Performance EVM

Calculateur de Gestion de la Valeur Acquise (EVM)

Maîtrisez les formules EVM essentielles pour les examens PMP/CAPM et le suivi des performances réelles des projets. Calculez l'IPC, l'ISC, l'EC, l'EV, l'EAC, et plus encore.

1Données du Projet

$
$
$
$

2Indices de Performance

CPI (Cost)
-
SPI (Schedule)
-

3Écarts

Cost Variance (CV)

EV - AC

-
Schedule Variance (SV)

EV - PV

-

EVM Formula Reference

Cost Variance (CV)

CV = EV - AC

Positive = Under budget

Schedule Variance (SV)

SV = EV - PV

Positive = Ahead of schedule

Cost Performance Index (CPI)

CPI = EV ÷ AC

>1.0 = Under budget

Schedule Performance Index (SPI)

SPI = EV ÷ PV

>1.0 = Ahead of schedule

Estimate at Completion (EAC)

EAC = BAC ÷ CPI

Projected total cost

Variance at Completion (VAC)

VAC = BAC - EAC

Expected budget variance

To Complete Performance Index (TCPI)

TCPI = (BAC - EV) ÷ (BAC - AC)

Required efficiency to meet BAC

Comprendre la Gestion de la Valeur Acquise

La Gestion de la Valeur Acquise (EVM) est une technique puissante de gestion de projet qui intègre les données de portée, de calendrier et de coût pour évaluer la performance et l'avancement du projet.

Indices de Performance

IPC > 1,0 signifie en dessous du budget ; < 1,0 signifie au-dessus du budget

Écarts

ISC > 1,0 signifie en avance sur le calendrier ; < 1,0 signifie en retard sur le calendrier

Prévisions

Un EC/EV positif est bon ; négatif indique des problèmes

Suivez les Performances Réelles du Projet

Utilisez les analyses intégrées d'Edworking pour suivre les performances réelles de votre projet en temps réel.