/EVM Performance Calculator

Earned Value Management (EVM) Calculator

Master the critical EVM formulas for PMP/CAPM exams and real-world project performance tracking. Calculate CPI, SPI, CV, SV, EAC, and more.

1Project Data

$
$
$
$

2Performance Indices

CPI (Cost)
-
SPI (Schedule)
-

3Variances

Cost Variance (CV)

EV - AC

-
Schedule Variance (SV)

EV - PV

-

EVM Formula Reference

Cost Variance (CV)

CV = EV - AC

Positive = Under budget

Schedule Variance (SV)

SV = EV - PV

Positive = Ahead of schedule

Cost Performance Index (CPI)

CPI = EV ÷ AC

>1.0 = Under budget

Schedule Performance Index (SPI)

SPI = EV ÷ PV

>1.0 = Ahead of schedule

Estimate at Completion (EAC)

EAC = BAC ÷ CPI

Projected total cost

Variance at Completion (VAC)

VAC = BAC - EAC

Expected budget variance

To Complete Performance Index (TCPI)

TCPI = (BAC - EV) ÷ (BAC - AC)

Required efficiency to meet BAC

Try Edworking Background

A new way to work from anywhere, for everyone for Free!

Get Started Now