/EVM Performance Calculator

EVM Calculator for CPI, SPI, EAC and TCPI

Calculate Earned Value Management metrics for PMP prep and project controls, then interpret cost, schedule, and forecast signals clearly.

1Project Data

$
$
$
$

2Performance Indices

CPI (Cost)
-
SPI (Schedule)
-

3Variances

Cost Variance (CV)

EV - AC

-
Schedule Variance (SV)

EV - PV

-

EVM Formula Reference

Cost Variance (CV)

CV = EV - AC

Positive = Under budget

Schedule Variance (SV)

SV = EV - PV

Positive = Ahead of schedule

Cost Performance Index (CPI)

CPI = EV ÷ AC

>1.0 = Under budget

Schedule Performance Index (SPI)

SPI = EV ÷ PV

>1.0 = Ahead of schedule

Estimate at Completion (EAC)

EAC = BAC ÷ CPI

Projected total cost

Variance at Completion (VAC)

VAC = BAC - EAC

Expected budget variance

To Complete Performance Index (TCPI)

TCPI = (BAC - EV) ÷ (BAC - AC)

Required efficiency to meet BAC

Use EVM results to guide project decisions

Earned Value Management is most useful when the numbers lead to action. Compare CPI, SPI, variance, and forecast values, then decide whether to adjust scope, budget, schedule, or team capacity.

Performance Indices

CPI above 1.0 means cost efficiency is healthy; below 1.0 means the project is spending faster than earned progress.

Variances

SPI above 1.0 means schedule progress is ahead of plan; below 1.0 means the team should inspect blockers and sequencing.

Forecasts

Positive variances are healthy, while negative variances should trigger a review of budget, delivery plan, or risk response.

Track EVM follow-up work in Edworking

After calculating CPI, SPI, EAC, or TCPI, turn corrective actions into tasks, document assumptions, and review progress with your team in one workspace.

Create a project workspace

A new way to work from anywhere, for everyone for Free!

Get Started Now