Sprint planning is the meeting that starts each sprint, where the whole Scrum team agrees why the sprint is valuable, what it can deliver and how the work will get done. This sprint planning meeting agenda fits a two-week sprint into 60 minutes and produces a sprint goal and a sprint backlog the developers believe in.

Agenda

60 min · 5 parts

  1. 0:00Last sprint10 minWhat got done, what carried over and what the review and retro changed
  2. 10:00Sprint goal10 minOne sentence on why this sprint is valuable
  3. 20:00Backlog25 minPick the items that serve the goal, size them and plan the first tasks
  4. 45:00Capacity10 minTime off, focus time and dependencies
  5. 55:00Commit5 minConfirm the goal and the plan, and who starts on what
Use this template

Free to start. Guests join from a link, no account needed.

Length
60 min
How often
On the first day of every sprint, after the previous sprint's review and retrospective.
Who attends
The whole Scrum team: the product owner, the developers and the Scrum Master, plus anyone invited to give advice.
You leave with
A sprint goal everyone can explain, the backlog items selected to reach it and a plan for the first days of work.

The agenda, part by part

How to run a sprint planning meeting

  1. 1. Last sprint

    10 min

    Start where the last sprint ended: what met the definition of done, what didn't, and why. Bring in feedback from the sprint review and the action from the retrospective, because both should shape this sprint. Decide what happens to unfinished work instead of rolling it over by default.

    Ask: What did we learn last sprint that should change this one?

  2. 2. Sprint goal

    10 min

    The product owner proposes how the product could become more valuable this sprint, and the team shapes it into one sentence. A good sprint goal describes an outcome, not a list of tickets, so the team can adapt the work and still meet it. Write it where everyone will see it all sprint.

    Ask: If we deliver only one thing this sprint, what should it be?

  3. 3. Backlog

    25 min

    Walk the top of the product backlog in order and select the items that serve the goal. The developers decide how much they can take on and break each item into tasks of a day or less. If an item isn't clear enough to start, leave it out rather than guess; refining before the meeting keeps this part short.

    Ask: Do we understand this item well enough to start it tomorrow?

  4. 4. Capacity

    10 min

    Check the selection against real availability: holidays, support duty, recurring meetings and work that depends on other teams. Use recent sprints as a guide, not a target. If the plan doesn't fit, cut items, not quality or the goal.

    Ask: Who is out, on call or shared with another team this sprint?

  5. 5. Commit

    5 min

    Read the sprint goal and the selected items aloud and ask whether the developers believe in the plan. In the 2020 Scrum Guide, the commitment is the sprint goal; the selected items are a forecast that can change as the team learns. Close by naming who starts on what tomorrow.

    Ask: From one to five, how confident are we in this plan?

Sprint planning questions to ask

  • What is the most valuable thing we could deliver this sprint?
  • Which items are ready to start, and which need more refinement?
  • What does done look like for each item?
  • Which dependencies or other teams could slow us down?
  • What did we leave unfinished last sprint, and does it still matter?
  • How much of our time is already taken by support or meetings?
  • What would we drop first if something unexpected comes up?

Example: planning a two-week sprint with a holiday

A team of six plans a sprint with a public holiday and one developer on leave for a week.

Notes

  • Last sprint: 7 of 9 items done; search filters carried over.
  • Sprint goal: new customers can import their contacts without help.
  • Selected: file import, field mapping, error report. Search filters go back to the product backlog.
  • Capacity: 9 working days; Kofi out the second week; Sara on support Monday and Tuesday.
  • Confidence vote: 4 out of 5. Risk: no test files large enough yet.

Action items

  • Ingrid (product owner): confirm import size limits with sales, by Wednesday.
  • Mateo: break field mapping into tasks, by the end of tomorrow.

Ways to adapt it

One-week sprints

Use the same sprint planning template in 30 to 45 minutes. Keep the look back to a few minutes and spend most of the time on the backlog.

Refine before you plan

Hold a backlog refinement session a few days before planning so items arrive clear and sized. The backlog part then becomes selection, not discovery.

Three- or four-week sprints

Split the meeting in two: the goal and the selection with the product owner first, then a separate session where the developers plan how they will build it.

Common mistakes

  • Choosing the backlog first and writing the goal last.

    Instead: Agree on why the sprint matters first. A goal written to describe whatever was picked won't guide any decision during the sprint.

  • Filling the sprint to 100% of capacity.

    Instead: Leave room for bugs, support and questions. A plan with some slack is one the team can actually finish.

  • Refining stories in the meeting.

    Instead: Refine the top of the backlog before planning. If an item still isn't clear, move it to a later sprint instead of guessing.

  • The product owner decides how much fits.

    Instead: The product owner brings the priorities. The developers decide how much they can take on and how they will build it.

Run it in Edworking

Your agenda keeps the meeting on time

Start a video meeting from any template. Edworking turns the agenda into the structure of the call, so nobody has to watch the clock.

Live agenda

A timer for every part

Everyone sees the agenda and how long is left in each part, with a clear moment when the meeting moves on.

AI notes

Notes that follow the agenda

AI takes the notes part by part and writes the summary and action items when the call ends.

Tabs in the call

Your work on screen, no sharing

Open docs, tasks and files as tabs in the call. Everyone sees the same thing without anyone sharing a screen.

Guests

Anyone can join from a link

Free to start. Clients, candidates and guests join from a link, with no account needed.

See how video calls work in Edworking

Frequently asked questions

The Scrum Guide sets a maximum of eight hours for a one-month sprint, and shorter sprints usually need less. With a refined backlog, a two-week sprint can often be planned in one to two hours; this agenda fits 60 minutes.